While managing a hybrid project that uses both agile and traditional methods, a project manager identifies in the planning phase that the unavailability of a key technical expert could jeopardize the schedule. This risk is formally recorded in the risk register with a defined response strategy. A week before this specialist is required, they unexpectedly go on leave due to a personal emergency.
Since this task lies on the critical path, the delay could impact the project timeline. What should the project manager do next?
A. Consult the risk register for an appropriate planned risk response and implement it
B. Revise the project management plan and reschedule the task based on resource availability
C. Reassess the business requirements with stakeholders and remove the task from the project scope
D. Update the lessons learned and the risk log to note that the risk has occurred
Correct Answer: A
Explanation:
When a risk becomes an actual issue, the project manager's priority is to act on pre-established plans rather than improvising under pressure. In this case, the risk was foreseen during the planning phase and documented in the risk register, which likely includes a defined mitigation or contingency plan. The correct step is to consult that register and implement the planned response immediately.
This course of action reflects best practices in risk management according to PMI’s PMBOK® Guide. It shows that the project manager has demonstrated proactive leadership by preparing for such situations. A pre-defined risk response might include reassigning the task to a backup resource, outsourcing the work, or rearranging less critical tasks to maintain the schedule. Implementing this plan helps avoid delays on the critical path and maintains control over project timelines.
Option B, while seemingly reasonable, implies rescheduling based on availability, which may have been considered already during risk planning. Option C alters project scope without proper stakeholder engagement or justification, which is inappropriate and potentially harmful. Option D, although important for future reference, is a follow-up action rather than an immediate response to the issue at hand.
Therefore, the most effective and responsible approach is A—leveraging the documented risk response to deal with the now-realized risk, ensuring a stable and disciplined management of project uncertainties.
A team that recently adopted agile methodology begins experiencing delays and confusion during daily stand-ups. Team members express concern about unclear requirements and frequent delivery setbacks. In an attempt to maintain the timeline, the project leader, instead of solving the root problems, instructs the team to fast-track features. This results in reduced quality and fewer features delivered per sprint.
What should the project leader have done to better support long-term project success?
A. Asked the team to create an impediment log and keep it updated for use in the next sprint planning
B. Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery
C. Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints
D. Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments
Correct Answer: D
Explanation:
The most effective way to resolve recurring delivery issues in agile teams is to enable them to self-improve and remove impediments collaboratively. Agile is built on principles of continuous improvement, self-organization, and team empowerment. In this case, the leader should have focused on fostering a culture where the team reflects on its challenges and works toward process improvements, rather than simply speeding up delivery.
Option D represents the core value of agile empowerment. By allowing the team to assess their tools, practices, and workflows, they can uncover the actual causes of delays—such as poor requirement clarification or inefficient communication—and implement changes that improve long-term velocity and product quality.
While fast-tracking features may appear to address short-term pressures, it usually results in technical debt, reduced quality, and low morale, which undermines agile’s goal of delivering value iteratively and sustainably. The leader’s role should have been to facilitate conversations during retrospectives or stand-ups that identify actionable improvements and foster team-led solutions.
Option A, tracking impediments, is helpful but doesn’t fix root issues by itself. Option B contradicts agile’s emphasis on team-driven problem-solving by prescribing external solutions. Option C treats impediments as backlog items, which delays resolution rather than enabling immediate process changes.
Ultimately, long-term success in agile environments is driven by empowered teams that can inspect, adapt, and grow. This makes D the best option, as it aligns with agile principles and encourages high performance without compromising quality or team dynamics.
Your Agile team consistently delivers working features at the end of each iteration. According to Agile practice, the customer is expected to review these deliverables during iteration review meetings. However, the customer frequently fails to attend these sessions, resulting in delayed feedback. Consequently, the team proceeds without customer input, often leading to unnecessary rework and reduced efficiency.
As the project manager, what is the best step you can take to ensure feedback is received promptly and rework is minimized?
A. Include the customer in daily stand-ups and other ongoing team activities for continuous feedback
B. Arrange a structured review schedule with the customer that aligns with their availability
C. Ask the customer to finalize and submit all requirements at the beginning of each iteration
D. Allow the customer to provide feedback whenever they are available, even if it causes delays
Correct Answer: B
Explanation:
In Agile environments, timely customer feedback is essential for ensuring the product evolves correctly and aligns with user expectations. Iteration reviews are designed to facilitate this feedback loop by allowing stakeholders to inspect the increment and provide guidance for future work. When the customer is routinely absent from these meetings, it interrupts the process, causing delays and potentially leading to misaligned deliverables.
Option B is the most appropriate response. It reflects proactive project management by identifying the customer's availability as the root issue and offering a structured solution. By coordinating with the customer to define a mutually convenient review schedule, the team can secure consistent input without disrupting the Agile cadence. This promotes smoother delivery cycles and minimizes the risk of costly rework.
Option A, although collaborative in spirit, may not be practical. Involving the customer in daily stand-ups may overextend their availability and introduce inefficiencies.
Option C violates Agile principles by assuming that requirements must be static. Agile encourages ongoing refinement and adaptation based on customer feedback.
Option D essentially avoids the problem, allowing delays to persist without mitigation, which undermines productivity and quality.
In summary, by engaging the customer early and setting a recurring, agreed-upon review schedule, the team can preserve the integrity of Agile workflows, reduce rework, and ensure consistent stakeholder engagement.
You are managing a time-critical project that involves updating a legacy application to meet a newly enforced regulation. With only six weeks remaining, a software engineer reports during a stand-up that work on a key feature is stalled, awaiting input from a designer. This dependency is now threatening the overall project timeline.
What is the best immediate action you should take to resolve this bottleneck and keep the project on track?
A. Escalate the issue by requesting an additional designer from the design team’s manager
B. Tell the engineer to move forward without the input from the designer
C. Ask the design manager to reprioritize tasks within their team
D. Speak directly with the designer to understand the delay and work together on a solution
Correct Answer: D
Explanation:
When working under tight deadlines, it's essential to resolve blockers quickly to avoid compromising delivery. In this situation, where a critical feature cannot progress without a designer’s input, immediate and effective action is necessary.
Option D is the most effective approach. By directly communicating with the designer, the project manager fosters transparency and encourages swift problem-solving. This conversation can uncover the specific reason for the delay—whether it’s workload, misunderstanding, or misalignment on priorities. The manager and designer can then jointly determine whether there are alternatives or workarounds that allow progress without compromising quality or regulatory compliance.
This direct engagement supports Agile principles of face-to-face communication, quick resolution of impediments, and empowered team collaboration. It also provides the project manager with firsthand insight, which can be valuable if further action (like escalation) becomes necessary.
Option A might help if more resources are truly needed, but it introduces delay and doesn’t solve the immediate issue.
Option B risks compromising the deliverable's completeness and may result in a product that fails to meet regulatory standards.
Option C defers resolution by adding another layer of communication and relies on a manager who may not fully understand the urgency of the specific task.
To maintain momentum and ensure compliance, the project manager must act decisively and collaboratively. Direct engagement with the designer is the most efficient and Agile-aligned way to overcome the current obstacle and stay on schedule.
A project manager is starting a new initiative in collaboration with a client who insists on beginning work immediately due to a regulatory deadline. However, many key product requirements remain unclear. Rather than using a fully predictive or agile approach, the project manager chooses a hybrid methodology.
Why is this hybrid approach the most appropriate for the project?
A. A hybrid model allows the team to initiate work even when all requirements aren't finalized
B. A hybrid method lets the manager change the product specifications at any time
C. A hybrid method effectively handles both the uncertain requirements and the fixed deadline
D. A hybrid model guarantees the deadline is met by removing all requirement uncertainties
Correct Answer: C
Explanation:
A hybrid project management approach blends both predictive (waterfall) and adaptive (agile) practices to tailor how a project is executed. This is especially useful when part of the project is well understood and time-sensitive, while other components remain unclear or likely to evolve.
In this case, the customer demands immediate progress because of a regulatory deadline, yet the scope is not fully defined. A traditional predictive approach would require complete documentation of all requirements before starting, which would delay the timeline. On the other hand, a fully agile model allows for evolving requirements but may not offer the control and predictability necessary to hit a fixed compliance deadline.
Choosing a hybrid approach (Answer C) enables the project manager to begin work on known, fixed components using predictive methods while handling evolving or unclear features with agile techniques. This dual structure provides the rigor needed to meet strict deadlines and the flexibility to adjust to requirement changes. It's ideal for regulated industries where compliance cannot be compromised but where product details may emerge gradually through customer collaboration.
Options A and B partially describe benefits of hybrid approaches but don’t fully capture the strategic balance between predictability and adaptability. Option D is incorrect because no methodology can eliminate uncertainty altogether—only manage it more effectively.
In summary, the hybrid method is the best choice here because it aligns with both key aspects of the project: a firm regulatory deadline and undefined product requirements, ensuring timely delivery while accommodating change.
A project manager is leading a team where all members are in the same time zone. However, some remote participants are experiencing collaboration challenges, leading to disengagement and concern from others. Although time differences aren't an issue, the manager suspects other factors may be hindering virtual teamwork.
What should be the project manager’s next step to improve collaboration?
A. Introduce new collaborative tools or technologies
B. Analyze the team’s virtual collaboration needs
C. Address potential violations of ground rules
D. Initiate a formal review of team member performance
Correct Answer: B
Explanation:
Even when team members work within the same time zone, remote collaboration can suffer due to issues unrelated to geography. In the given scenario, some remote members feel disconnected from the team, which suggests that communication norms, tools, or expectations for virtual collaboration may not be working effectively.
The most appropriate next step is to examine the team’s virtual needs (Answer B). This means evaluating whether the current collaboration tools (e.g., video conferencing, chat platforms, file sharing) are adequate and accessible to all team members. It also involves assessing the team’s working norms, such as expectations for responsiveness, participation in meetings, and shared understanding of roles and responsibilities in a remote environment.
Engagement can also be influenced by soft factors, including digital fatigue, lack of clarity in communication, or even a lack of psychological safety in virtual settings. These barriers may not be immediately visible but can significantly affect collaboration.
Option A, introducing new tools, is a possible solution—but doing so without first understanding the actual issues could lead to wasted resources or even further confusion. Option C, addressing ground rule violations, presumes that rules have already been broken, which hasn't been confirmed. Option D, conducting a performance review, addresses individual outcomes rather than addressing the root systemic or environmental issues affecting collaboration.
By first analyzing the team’s virtual needs, the project manager can gain insight into what’s really affecting collaboration—be it technological, procedural, or cultural—and take informed action to enhance team cohesion and productivity.
A multinational company is working on a project involving team members who are dispersed across different countries and time zones. While individuals are completing their assigned work effectively, the team's overall performance is declining, particularly with collaborative tasks and joint responsibilities. There’s a clear gap in coordination, and team unity is lacking.
What should the project manager do to strengthen team collaboration and boost effectiveness?
A. Reassign tasks among team members
B. Promote better communication and organize team-building activities
C. Request different team members from the resource manager
D. Modify the communications management plan
Correct Answer: B
Explanation:
When managing distributed or virtual teams, one of the most common and impactful challenges is maintaining strong team communication and a sense of cohesion. In this situation, the issue is not with individual performance, which is satisfactory, but rather with how the team functions as a unit. This points to a lack of interpersonal synergy, which is essential for successful collaboration—especially when members are located in different geographic and time zones.
The most effective action a project manager can take is to facilitate communication and team-building efforts. This can involve organizing virtual meetings where people can connect on both professional and informal levels, encouraging open communication, and implementing collaboration tools that bridge the physical gap. It may also help to establish overlapping work hours for synchronous activities or rotate meeting times to accommodate different time zones.
Team-building initiatives, even in virtual formats, can help team members build trust, understand each other’s strengths, and form personal connections that lead to more seamless collaboration. These steps can directly improve team dynamics, increase engagement, and ultimately lead to better project outcomes.
Choosing to reassign tasks (Option A) does not resolve the underlying issue of team cohesion. Similarly, requesting new team members (Option C) is extreme and unnecessary when individual performance is not the problem. While updating the communications management plan (Option D) may improve communication logistics, it doesn't directly address interpersonal relationships and team trust, which are central to effective teamwork.
Therefore, fostering open communication and strengthening team bonds through team-building is the most strategic and human-centered approach. It supports long-term collaboration and enhances the group’s ability to perform shared tasks effectively.
In the third sprint of an ongoing agile project, the product owner introduces another must-have feature. This has become a pattern across previous sprints, leading to missed sprint goals and increasing frustration among the development team. The team is now worried about scope creep, low morale, and disrupted timelines.
What is the most appropriate response the project manager should take to address this issue?
A. Ask the development team to reorder the product backlog
B. Involve the product owner and the project team in reprioritizing the backlog
C. Conduct a team-only meeting to assess the impact of these changes
D. Delay the new feature to the final sprint before launch
Correct Answer: B
Explanation:
In agile methodologies like Scrum, the product backlog is a dynamic list of all desired work on the project. The product owner (PO) is responsible for managing and prioritizing this backlog. However, effective prioritization should be done in collaboration with the development team to ensure that what's planned for each sprint is both feasible and valuable.
In this scenario, repeated last-minute additions by the product owner are causing sprint commitments to be missed, which undermines one of Scrum's core principles—sustainable pace and predictability. It also frustrates the development team, decreases morale, and signals a lack of effective backlog grooming.
The ideal resolution is for the product owner and the team to work together on backlog prioritization (Option B). This collaborative approach ensures that all stakeholders understand the capacity and limitations of the sprint. It also allows developers to estimate new work, discuss trade-offs, and commit only to what they can realistically achieve. This reinforces trust, ensures better planning, and guards against future scope creep.
Option A suggests the development team take ownership of backlog prioritization, which misaligns with Scrum roles—the PO owns the backlog, not the team. Option C, holding a meeting without the product owner, might allow team members to express their frustrations but won’t resolve the fundamental issue of uncontrolled scope changes. Option D (delaying changes to the final sprint) is risky—it postpones addressing the scope creep and does not fix the systemic issue of poor planning and communication.
By involving both the product owner and the team in backlog management, the project manager reinforces agile principles, ensures smoother delivery, and fosters a culture of mutual accountability and transparency.
During a multi-team Agile project, each team seemed to be progressing well when assessed individually. However, significant issues surfaced during mid-project integration, causing delays and casting doubt on meeting feature delivery timelines.
What should the project manager have implemented earlier to avoid these integration setbacks and ensure steady project progress?
A. Conducted regular Scrum of Scrums to help teams address blockers collaboratively
B. Created a dedicated QA team to perform end-of-sprint testing for each team’s output
C. Delivered training sessions on integration strategies and relevant tools to the teams
D. Ensured regular and continuous integration of outputs to catch issues early and promote learning
Correct Answer: D
Explanation:
When managing Agile projects involving several teams working on a shared product, continuous integration (CI) is essential to avoid last-minute surprises and ensure alignment across teams. While each team might complete their deliverables on time, failing to integrate regularly leads to a buildup of unseen issues that only surface during full product integration. This scenario reflects the classic problem of deferred integration, where coordination problems and technical incompatibilities accumulate unnoticed.
CI is the practice of integrating work frequently—often daily or after completing each user story—so that issues are discovered early, and teams can respond quickly. This not only minimizes technical debt but also fosters collaboration and a shared understanding of the end product. Teams get immediate feedback on whether their code or features work with the rest of the system, which dramatically reduces rework later.
Option A, using Scrum of Scrums, enhances inter-team communication but doesn’t solve the technical integration challenges. It might help identify blockers, but it won’t uncover code or system conflicts. Option B, forming a separate QA team, introduces a waterfall-like delay and doesn’t align with Agile principles that emphasize shared ownership of quality. Option C, training on tools and strategies, is helpful for awareness but insufficient on its own to ensure integration actually happens.
Only Option D supports both Agile and Lean values by advocating for frequent, continuous integration, promoting early validation, quick error detection, and incremental delivery. This approach not only helps maintain momentum but also promotes team accountability for the overall system, not just isolated components.
A project is falling behind schedule because a capable team member is struggling with tasks that involve a recently introduced system. The root cause is their lack of familiarity with the new system, not their general competence.
How should the project manager respond to keep the project on track without demoralizing the team?
A. Ask the team member to learn the new system as on-the-job training
B. Issue a change request to extend the project schedule
C. Escalate the team member's performance to the project sponsor
D. Assign an experienced resource to support the team member
Correct Answer: D
Explanation:
In Agile and traditional project management alike, a project manager’s responsibility includes proactively supporting team members to overcome performance hurdles, especially when the issue stems from a skill gap rather than lack of effort. In this situation, the team member is otherwise competent but is struggling due to unfamiliarity with a new system. The most appropriate response is to assign an experienced resource to work alongside them (Option D).
This approach enables knowledge transfer, allowing the struggling team member to gain the necessary skills more quickly and with guided support. It helps preserve project momentum while also strengthening team capacity in the long run. Peer support can improve learning efficiency, build team morale, and reinforce a collaborative culture. It’s a solution that is both pragmatic and empathetic, key traits of effective leadership.
Option A, asking the team member to learn the system independently, might seem efficient but often leads to slow progress and growing frustration. Learning under pressure without guidance can lower productivity and team morale. Option B, requesting a project delay, addresses the symptom rather than the cause, and is typically a last resort when all internal remedies have failed. Option C, escalating the issue to the sponsor, is premature and could damage trust within the team, especially when a supportive solution hasn’t yet been attempted.
By choosing Option D, the project manager keeps the project timeline intact while providing hands-on development opportunities. This method demonstrates leadership maturity—choosing to coach and enable rather than blame or escalate unnecessarily. It also reflects a servant leadership mindset, one that puts team support and success first, which is especially valued in Agile environments.
Site Search:
SPECIAL OFFER: GET 10% OFF
Pass your Exam with ExamCollection's PREMIUM files!
SPECIAL OFFER: GET 10% OFF
Use Discount Code:
MIN10OFF
A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.
Download Free Demo of VCE Exam Simulator
Experience Avanset VCE Exam Simulator for yourself.
Simply submit your e-mail address below to get started with our interactive software demo of your free trial.