Project Management Professional (2025 Version)
Last Update 3 days ago
Total Questions : 594
Project-Management-Professional is stable now with all latest exam questions are added 3 days ago. Incorporating PMP practice exam questions into your study plan is more than just a preparation strategy.
PMP exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through PMP dumps allows you to practice pacing yourself, ensuring that you can complete all Project-Management-Professional practice test within the allotted time frame.
A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.
What should the project manager review during the management review to ensure the meeting is effective?
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.
What should the project manager do?
A project lead with a strong technical background oversees a project using agile delivery. The product owner asked the project lead to assist with ensuring the benefits of functionality that are built in the sprint are tracked.
What should the project lead advise?
A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.
What should the project manager do to address this concern?
A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.
How should the project manager plan this project?
A company in the manufacturing industry has started a new initiative to integrate project management and improve product innovation. What first step should the project manager take to increase transparency among the stakeholders?
A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.
A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.
What should the project manager do to address the issue?
A project team is working together for the first time. During the first sprint, the project manager was asked to solve a prioritization conflict between the Scrum Master and the Product Owner related to a feature requested by an important customer.
How should the project manager resolve this conflict?
A project has recently completed its production go-live, meeting the project's completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements.
How should the project manager address the customer's requests?
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.
What should the project manager do?
An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.
What should the project manager do?
During project execution, a key stakeholder approaches the project manager and questions the business value of the project. What should the project manager do?
An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.
What should the project manager do first to resolve this dispute?
TESTED 29 Oct 2025
Hi this is Romona Kearns from Holland and I would like to tell you that I passed my exam with the use of exams4sure dumps. I got same questions in my exam that I prepared from your test engine software. I will recommend your site to all my friends for sure.
Our all material is important and it will be handy for you. If you have short time for exam so, we are sure with the use of it you will pass it easily with good marks. If you will not pass so, you could feel free to claim your refund. We will give 100% money back guarantee if our customers will not satisfy with our products.